Over a million developers have joined DZone.
{{announcement.body}}
{{announcement.title}}

3 Reasons to Estimate With Story Points

DZone's Guide to

3 Reasons to Estimate With Story Points

Are Story Points really better than man hours? Read one author's take on the debate.

· Agile Zone
Free Resource

Reduce testing time & get feedback faster through automation. Read the Benefits of Parallel Testing, brought to you in partnership with Sauce Labs.

In our previous article about estimating with Story Points, we concluded that Story Points are a handy and efficient measurement technique for estimating the amount of effort a team needs to develop a particular feature. Now, we’d like to talk about why, here at RubyGarage, we prefer estimating in Story Points as opposed to man hours.

Man Hours: What Are They and Why Don’t They Work for Us?

story points estimating

Estimating in man hours is one of the most widespread approaches for estimating the amount of work in a team. It relies on an estimate of the amount of work that can be completed by one person within one hour. While man hours are easy to understand, there are a few big drawbacks to this technique:

  • Some tasks are difficult to estimate precisely.
  • If one developer estimates a project but another completes the task, the estimate becomes invalid. The time needed to complete a task will vary based on a developer’s level of experience.
  • People generally underestimate obstacles they might face and consider only the best-case scenario.

The bottom line is that drawbacks of estimating in man hours outweigh the advantages and bring value neither to RubyGarage nor to our clients. But there are multiple reasons why we like estimating in Story Points.

Why Story Points?

With man hours, developers expect that they’ll log the exact number of hours estimated for the Sprint. That’s a double-edged sword. If they exceed the number of hours estimated for a Sprint, then it suggests they’re a poor performer. If they complete the Sprint under the estimated number of hours, then it means that there was something wrong with the estimate.

Story Points offer three main advantages over man hours.

1. No Correlation With Skills and Experience of the Estimator

As we already mentioned, a specialist who estimates a task isn’t always the one who implements it. Senior and Junior developers need different amounts of time to complete the same task. The only way to avoid all this is to make a developer who estimates a project also implement that project.

Story Points eliminate this problem. Story Points are a universal measurement across the whole team. The estimate doesn’t depend on who’s implementing the story. All team members, with different skill levels, can discuss the estimate together and come to a single conclusion.

Estimate with Story Points

The whole team can get a clear understanding of the story size and complexity. This is the main advantage of story points.

2. Velocity Is Tracked

Another key to the power of Story Points estimation is velocity. Velocity is a powerful capacity planning method that demonstrates how much product backlog effort a software development team can successfully handle in one Sprint. The goal of a team is to raise its velocity.

Team members discuss ways to achieve greater velocity during retrospectives after each Sprint. The higher the team's velocity, the higher the team's capacity to perform a given task quicker and more efficiently.

Velocity is a relative value that can change during the course of the project. And here, we find the next advantage of estimating with Story Points – you will not need to re-estimate your project if velocity changes, whereas estimating in man hours would require you to perform a recalculation.

3. No Re-Estimation if Velocity Changes (Flexibility)

Another value of estimating with Story Points is that they let you re-plan product release deadlines without re-estimating all tasks if members of the team are changed.

It often happens that one person estimates a project, but other people complete the tasks. In this case, Story Points are indispensable.

Story points vs hours

Let’s consider several examples.

Example 1

Our company has a project estimated at 200 Story Points. One developer starts working on it. His velocity is 1 SP per 3 hours. The start date is May 30th. Based on this information, it’s easy to calculate the project release date.

The time needed to finish all the work:

T = Qsp*t,

(Where Qsp is the general quantity of SP in the project and t is the time to complete 1 SP)

200 x 3 = 600 (hours).

The number of workdays:

Nw=T/Prt,

(Where Nw is number of workdays, T is the time needed to finish all the work, and Prt is the quantity of productive hours in the working day, usually six hours)

600 / 6 = 100 (workdays).

Having a calendar at hand, we can then calculate a release date — October 14th.

If for some reason, we change the developer and the new developer works with the velocity of 1 SP per 1.5 hours, then we can quickly re-calculate our date. Now, the number of workdays required is 50 and our date of release will be August 5th.

Example 2

Our project is estimated at 200 SP. The team fulfills 40 SP during one Sprint. We know that one Sprint is equal to two weeks.The start date is May 30th. Let’s calculate:

T = Ns*t

(Where T is the general time for completion of the whole project, Ns is the number of Sprints in the project, and t is the time needed for one Sprint)

(200/40)*2 = 10 (weeks).

The release date is August 8th.

Let’s say that some changes have occurred, and the velocity of the team has changed. Now the team completes 50 SP during one Sprint. It will be easy to re-calculate our date.

(200/50)*2 = 8 (weeks).

The release date is now July 25th. Thus, Story Points allow our Product Owner to see more precise release dates after any changes in the team.

You see that we can convert abstract Story Points into more understandable days without any problems. We monitor the whole development process and can change it at any stage if it is necessary.

Let’s Sum Up

Story Points have acquired a reputation as a stable index that’s independent of the skill or experience of team members, lets you track a team’s velocity, and helps you stay flexible in re-planning project release dates.

Recently, some specialists have begun using a combination of both Story Points and man hours. But still, on the basis of our own experience, we are confident that Story Points offer the greatest utility for high-level planning.

The Agile Zone is brought to you in partnership with Sauce Labs. Discover how to optimize your DevOps workflows with our cloud-based automated testing infrastructure.

Topics:
story points ,agile ,sprints

Published at DZone with permission of Viktoria Kotsurenko. See the original article here.

Opinions expressed by DZone contributors are their own.

THE DZONE NEWSLETTER

Dev Resources & Solutions Straight to Your Inbox

Thanks for subscribing!

Awesome! Check your inbox to verify your email so you can start receiving the latest in tech news and resources.

X

{{ parent.title || parent.header.title}}

{{ parent.tldr }}

{{ parent.urlSource.name }}