What is the Right Iteration Length?

· Agile Zone

Learn more about how DevOps teams must adopt a more agile development process, working in parallel instead of waiting on other teams to finish their components or for resources to become available, brought to you in partnership with CA Technologies.

When picking iteration length for an agile project, there are mainly two forces that you have to balance: The rate of learning is proportional with the number of iterations, rather than the length of the project. This means that shorter iterations help you get better faster. But each iteration has some overhead with sprint reviews, retrospectives and planning. You don’t want this overhead to dominate the effort spent on the project.

For some reason, most projects I’ve seen with little experience in iterative development prefer three week iterations. Personally, I prefer two week iterations. Here is the breakdown:

  • Three week iterations: After three months, you’ve spent about 7% of your time on iteration meetings. You’ve had 4 opportunities to improve.

  • Two week iterations: After three months, you’ve spent about 10% of your time on iteration meetings. You’ve had 6 opportunities to improve.

  • One week iterations: After three months, you’ve spent about 20% of your time on iteration meetings. You’ve had 12 opportunities to improve.

Going from 93% to 90% efficiency for a 50% increase in learning seems like a good deal. Going from 90% to 80% efficiency for a 100% increase in learning, not so much.

These numbers are of course greatly simplified. You might also consider:

  • With shorter iterations, the planning time may go down. But this takes practice – it doesn’t happen automatically.

  • With very short iterations, you may not have experienced enough to learn much from the retrospective. However, if you find that you do a timeline, and most of the things people remember happened the last week, it may not be because that’s the only time something significant happened.

  • You may consider different frequencies for different ceremonies. For example, on my current project we want to have demos with our power users. But they have to travel far to visit us. So we only have a full demo every other four weeks. We plan every two weeks and have an internal review and retrospective every two weeks.

What’s the right iteration length for your project?

Discover the warning signs of DevOps Dysfunction and learn how to get back on the right track, brought to you in partnership with CA Technologies.

Topics:

Published at DZone with permission of Johannes Brodwall, DZone MVB. See the original article here.

Opinions expressed by DZone contributors are their own.

The best of DZone straight to your inbox.

SEE AN EXAMPLE
Please provide a valid email address.

Thanks for subscribing!

Awesome! Check your inbox to verify your email so you can start receiving the latest in tech news and resources.
Subscribe

{{ parent.title || parent.header.title}}

{{ parent.tldr }}

{{ parent.urlSource.name }}